One of the most common questions from indoor playground investors is:
“How long does it take from order confirmation to opening?”
The answer depends on project size, design complexity, and site conditions—but the overall process follows a clear and predictable timeline.
This article explains each stage of the indoor playground installation process, helping you plan realistically and avoid unnecessary delays.
This stage defines the entire project timeline.
Key tasks include:
Finalizing floor plan and play zones
Confirming ceiling height and column positions
Selecting themes, colors, and key attractions
Safety standard alignment (ASTM / EN)
Important:
Any design changes after this stage may affect manufacturing time.
Once the design is approved, production begins.
Typical manufacturing tasks:
Steel frame fabrication
Soft play components and net systems
Slides, tunnels, and themed panels
Safety padding and flooring materials
Project complexity determines production length:
Small projects: ~3–4 weeks
Large or customized parks: ~5–6 weeks
After manufacturing:
Equipment is pre-assembled and tested
Packed by installation sequence
Loaded into containers
Shipping time depends on destination:
Asia: 5–15 days
Europe: 25–35 days
Americas: 30–45 days
While equipment is in production or transit, the site should be prepared.
This includes:
Flooring leveling
Electrical and lighting installation
Fire safety systems
HVAC and ventilation
Good coordination here can save weeks overall.
Installation time depends on:
Playground size
Height and complexity
Local labor experience
Typical installation process:
Steel structure assembly
Platform and deck installation
Netting and soft play components
Slides and interactive elements
Final safety padding and flooring
Before opening:
Structural inspection
Safety checks (fall zones, clearances)
Equipment testing
Minor adjustments
This stage is essential for:
Insurance approval
Local authority inspections
Most operators run:
Soft opening / trial days
Staff training sessions
Emergency procedure drills
This ensures:
Smooth operations
Improved guest experience
Reduced early-stage issues
| Stage | Time |
|---|---|
| Design confirmation | 1–2 weeks |
| Manufacturing | 3–6 weeks |
| Shipping | 1–6 weeks |
| Installation | 1–3 weeks |
| Inspection & opening | 1 week |
| Total | 8–16 weeks |
A successful indoor playground project depends on planning, coordination, and realistic timelines.
Understanding each stage allows investors to:
Control costs
Avoid delays
Open on schedule
A clear installation timeline is not just operational—it is a key part of project success.
Safety compliance also impacts overall investment.
For a practical cost overview related to safety standards, see:
How Much Does an Indoor Playground Cost?
Copyright Wenzhou Dream Garden Amusement Equipment Co.,Ltd
AK 60175900 | ![]()